This Phase 2 project is new construction on the Maui Lani parcel. Initial application for 241 units, 123 units serving 80% AMI or less and 118 units serving 120% AMI or less. RFI revised to 290 units.
April 2026: Project conditionally awarded CDBG-DR funds
June 2026: Project design underway
July 2026: Environmental Review initiated