Replacement of two wastewater pump stations severely damaged by the disaster and evaluation of alternatives for potential relocation of Pump Station 5 to accommodate community planning initiatives.
May 2025: FEMA PA Funding Initial Approval
July 2025: Lahaina Royal Complex planning started, which will contribute to determination of potential relocation of Pump Station 5.
November 2025: Design Started
March 2026: Project Conditionally Awarded CDBG-DR Funds
July 2026: County of Maui selects alternative to relocate Pump Station 5 offsite from Moku'ula